Business Moving Group

office move

Office Move Checklist and Timeline for a Smooth Relocation

Office Move Checklist and Timeline for a Smooth Relocation

A strong office move is a project with clear scope, owners, and dates. Use this simple playbook to protect productivity, control costs, and keep your team focused on work while the move happens in the background.

Six week office move timeline

Week Primary goals Key deliverables
Week 6 Confirm new space requirements and building rules Final floor plan, elevator and dock reservations, proof of insurance, security access list
Week 5 Inventory and scope Asset count for workstations, files, IT, printers, kitchen, storage, artwork, signage
Week 4 Labels and packing plan Color zone map, room codes, label packs, packing assignments, supply list
Week 3 IT cutover plan Network and power layout, rack move plan, backup and restore steps, provider change orders
Week 2 Protection and permits Masonite routes, corner guards, door jamb covers, parking plan, any local permits required
Week 1 Final confirmations Move day schedule, crew counts, sequence of floors, after hours approvals, emergency contacts
Move week Execute and verify Load out, transport, load in, build and place, network checks, walk through and sign off

Roles that keep the move on track

Workstream Owner at your company Partner support from Business Moving Group
Project control and timeline Operations lead Detailed schedule, daily updates, issue tracking
Building coordination Office manager COI, elevator and dock bookings, site protection
IT cutover IT lead Server and rack handling, cable dressing, desk tech reconnect
Furniture and layout Facilities lead Deinstall and reinstall, leveling, anchoring, punch list
Packing and labels Team leads Supplies, training, zone map, label audit
Decommission and disposal Facilities lead E waste recycling, furniture donation, broom clean delivery

How to label and pack so nothing is lost

  1. Assign a color to each zone or department.

  2. Give every workstation a code that matches the new floor plan, for example 3B 14.

  3. Place the label on the top left of each box, the chair back, the monitor, the CPU, and the pedestal.

  4. Pack heavy items in small boxes and light items in larger boxes.

  5. Lock file cabinets and tag keys in a zip bag inside the top drawer.

  6. Snap a photo of any special setup so it can be rebuilt exactly the same at the new site.

See the EPA guide on electronics donation and recycling for compliant e waste handling.

IT cutover without surprises

Back up critical systems before any disconnect. Confirm power, network, and cooling at the new site. Move servers and network gear in dedicated cases with anti static protection. Stage racks in order, route power first, then data. Use a device list to verify every serial number that leaves the old site arrives at the new site. Schedule a smoke test that includes internet, shared drives, printers, and conference rooms.

Furniture and installation

Decide what moves, what is reconfigured, and what should be replaced. Provide drawings with final counts for workstations, private offices, conference rooms, and shared spaces. On arrival, installers set level and secure items, anchor where required, and adjust drawer faces and doors so lines are even. Keep a punch list and close it the same day.

Building protection and access

Protect floors with runners, cover corners, pad door frames, and cap sprinklers where needed. Lock in loading times with the building. Confirm height and length limits for the dock. Reserve parking for trucks and a staging area near the elevator. Share a contact list that includes security, property management, your team leads, and the move supervisor.

Decommission the old space

Remove all items that are not part of the new lease. Patch minor wall holes, sweep, and leave the space in broom clean condition. Provide receipts for e waste and donation so your team can log the environmental benefit. Photograph the space after handoff.

Move day playbook

  1. Crew arrives early, sets protection, and walks the routes.

  2. Foreman reviews the sequence and safety briefing with the team.

  3. Dispatch loads by zone so trucks deliver in the correct order.

  4. At the new site, crews build and place by zone, then reconnect tech.

  5. Supervisor checks against the label map and closes any gaps before sign off.

Office Moving Services
Place in the intro after project with clear scope to drive service relevance.

After move support

Run a help desk for the first week with a simple form. Capture chair height changes, monitor arm tweaks, extra power strips, and missing items. Close each request within one business day. Schedule a final walkthrough with facilities and IT to confirm the space is fully operational.

How Business Moving Group helps

Planning and project control from first call to final sign off
Protected routes and building coordination that keep property managers happy
Professional packing support and a clear label system
IT handling and desk tech reconnect that shortens downtime
Furniture deinstall and reinstall with punch list closeout
Decommission, donation, and e waste with documented chain of custody

Common cost levers you can control

Lever How to reduce cost
Elevator and dock time Book exclusive windows to avoid idle crews
Packing effort Purge and digitize before move week
IT downtime Stage and test the network in advance
Furniture scope Reuse and reconfigure where possible
Access issues Pre approve after hours work and security escorts
Change orders Freeze counts one week before the move

Final checklist before you sign off

  • Every workstation labeled and in place

  • All network ports live and tested

  • Conference rooms online with screens and audio

  • Printers mapped and printing

  • Kitchen and break areas stocked and ready

  • Old space cleared and documented

  • Punch list closed

Ready to Simplify Your Business Move?
Contact Business Moving Group today for a free consultation!
Visit us at Business Moving Group for helpful resources and to learn more about our services.

Share with us: